During the build of our extension the builder built the walls (outer and inner) before laying the slab. This means the DPM does not go under the course of blocks containing the DPC.
Is this a normal practice these days?
There is also a gap between the end of DPM in places and the DPC, can this be joined effectively to provide a complete damp proof barrier?
Image attached.
thanks in advance.