Hi Guys,
I am in the process of fully refurbishing my upstairs bathroom, with a new suite. All of which shall be put into the same place due to the space restriction. Below is my current bathroom & floor plan which you can tell is a small bathroom.
I would like the new bath, basin cabinet & toilet to be in the same place and for new controls to be installed as a concealed thermostatics on the wall and for the new bath to have an overflow bath filler, as opposed to taps. And above the bath on the wall to have a concealed shower head.
Ideally, new pipes would have to be run up the wall for the concealed kit (Thermostats & shower head), additionally to the bathroom overflow filler. Though everything else should be easily attached without any major pipework changes.
Ultimately I just want to get the bathroom suite done in the cheapest efficient/effective way possibly professionally. Sadly I have had 4 bathroom fitters in and all have quoted me above £3000 - £4500 just for labour fitting the suite in and tiling the walls and floors. Disposal of the old bathroom would go in my skip which is on my driveway.
On reviewing my pictures and dimensions below, how much do you guys think I should be paying? bearing in that this is for labour only not for the bathroom suite or fittings etc.. I will be supplying these.
I was thinking just calling a plumber in to put the new bathroom, toilet, basin cabinet and thermostatic valve. Then have a tiler to do the flooring, walls and electrician etc..basically guys from different trades to carry out the works individually.
I have carried out this rule of thumb through my home reno and have found it cheaper as opposed to having one person carry out a job. Sadly bathroom fitters, in my opinion, are too pricey.
I am now thinking of just hiring individual people and carrying out the bathroom refurb in the following order below.
1)Remove bathroom suite Dispose of - in skip. (plumber)
2)Remove tiles (I will do this or a tiler)
3)Replace window in external wall (joiner who I know)
4)install ventilation (electrician who I can bring in)
5)plaster everything (plasterer)
6)install new suite & thermostatic kit (plumber)
7)Tile (I'm a tiler and can do this)
8)install lights (electrician who I can bring in)
Is this order correct and your thoughts, please? thanks to all in advance.
below are the photos, the red circle on the second photo is a guide as to where I would like my concealed thermostatic placement and overhead shower head, I may need a slight extra partition in order to centre this nicely on the left side of the window. This shall be done when i order the new window which will then be smaller and fitted.
thank you all in advance.
I am in the process of fully refurbishing my upstairs bathroom, with a new suite. All of which shall be put into the same place due to the space restriction. Below is my current bathroom & floor plan which you can tell is a small bathroom.
I would like the new bath, basin cabinet & toilet to be in the same place and for new controls to be installed as a concealed thermostatics on the wall and for the new bath to have an overflow bath filler, as opposed to taps. And above the bath on the wall to have a concealed shower head.
Ideally, new pipes would have to be run up the wall for the concealed kit (Thermostats & shower head), additionally to the bathroom overflow filler. Though everything else should be easily attached without any major pipework changes.
Ultimately I just want to get the bathroom suite done in the cheapest efficient/effective way possibly professionally. Sadly I have had 4 bathroom fitters in and all have quoted me above £3000 - £4500 just for labour fitting the suite in and tiling the walls and floors. Disposal of the old bathroom would go in my skip which is on my driveway.
On reviewing my pictures and dimensions below, how much do you guys think I should be paying? bearing in that this is for labour only not for the bathroom suite or fittings etc.. I will be supplying these.
I was thinking just calling a plumber in to put the new bathroom, toilet, basin cabinet and thermostatic valve. Then have a tiler to do the flooring, walls and electrician etc..basically guys from different trades to carry out the works individually.
I have carried out this rule of thumb through my home reno and have found it cheaper as opposed to having one person carry out a job. Sadly bathroom fitters, in my opinion, are too pricey.
I am now thinking of just hiring individual people and carrying out the bathroom refurb in the following order below.
1)Remove bathroom suite Dispose of - in skip. (plumber)
2)Remove tiles (I will do this or a tiler)
3)Replace window in external wall (joiner who I know)
4)install ventilation (electrician who I can bring in)
5)plaster everything (plasterer)
6)install new suite & thermostatic kit (plumber)
7)Tile (I'm a tiler and can do this)
8)install lights (electrician who I can bring in)
Is this order correct and your thoughts, please? thanks to all in advance.
below are the photos, the red circle on the second photo is a guide as to where I would like my concealed thermostatic placement and overhead shower head, I may need a slight extra partition in order to centre this nicely on the left side of the window. This shall be done when i order the new window which will then be smaller and fitted.
thank you all in advance.