Hi, looking for a bit of advice please regarding the flooring in our 1960s house.

We moved in to our renovation project recently and we are looking to move the kitchen into a kitchen/diner room at the rear. After lifting the carpet/underlay in the room that will form the kitchen, we discovered original parquet flooring (Hewetsons of Hull) which had raised in some areas.
The blocks have been bonded down to a concrete slab with Bitumen, which from reading on here appears to also function as a DPM. It is a very thin layer as can be seen in the first pic and it is currently stinking the place out!
The outer wall construction is brick with a DPC, the inner wall construction is also brick but I cannot see a DPC.
The intention is to install a wet underfloor heating system and LVT flooring in this kitchen/diner. I've been advised to use Arditex NA, a liquid DPM, Arditex NA, then the underfloor heating.
However the concrete slab appears to have quite a lot of cracking and has lifted/sunk in various areas. When tapping one of the sections near the wall next to a crack it sounds a bit hollow underneath.
I am going to assume the diner floor is going to be the same when we lift that. To give an idea of size, the sales floor plan had the kitchen at 4.39x3.06m and the diner at 4.54x4.07m.

Should I still follow our original plan with self levelling compound or should I be looking at getting the concrete slab replaced? Is this a DIY job? I've completed a large patio before with compacted MOT1, Wet concrete bed and porcelain paving but not done any screeding/levelling previously.

With regards to dampness levels of the house, the house was empty for around a year, we viewed it a few times, one in January when it was frosty outside, we never noticed or smelled any damp. We have some large maturing trees nearby.

thanks
 

Attachments

  • 20230807_143750.jpg
    20230807_143750.jpg
    368.6 KB · Views: 83
  • 20230915_080050.jpg
    20230915_080050.jpg
    621.3 KB · Views: 72
  • 20230915_080102.jpg
    20230915_080102.jpg
    443.5 KB · Views: 103
  • 20230915_080109.jpg
    20230915_080109.jpg
    556.7 KB · Views: 93
  • 20230915_080136.jpg
    20230915_080136.jpg
    848.6 KB · Views: 85
  • 20230915_080145.jpg
    20230915_080145.jpg
    818.9 KB · Views: 81
  • 20230915_080227.jpg
    20230915_080227.jpg
    666.2 KB · Views: 72
  • 20230915_080251.jpg
    20230915_080251.jpg
    711.2 KB · Views: 74
Also just to add the ceiling height is 2460 from the concrete slab.
Hallway flooring level (asbestos tiles under the carpet) is 20mm above the concrete.

We were looking at the LoProx Max UFH heating system which gives a build up of 22mm.
 