I am trying to convert my Victorian out building into a summer house / gym. The floor is brick and very damp but also has a slope of about 7cm across 3.5m it is also very uneven. I have already put a DPC into the walls and now I need to damp proof and level the floor. Should I:
1) flatten the floor using soft sand (to prevent DPM tearing) lay a DPM and then a concrete slab to level.
Or
2) lay a concrete slab to level onto the brick and then tank / use a liquid dpm
Or
3) another method... I’m open to suggestions.
I am a little concerned that with option 1 the weight of the concrete slab will be pushing against the single down hill wall.
Thanks in advance for the help
1) flatten the floor using soft sand (to prevent DPM tearing) lay a DPM and then a concrete slab to level.
Or
2) lay a concrete slab to level onto the brick and then tank / use a liquid dpm
Or
3) another method... I’m open to suggestions.
I am a little concerned that with option 1 the weight of the concrete slab will be pushing against the single down hill wall.
Thanks in advance for the help