Hello
I've had a new 8L expansion vessel fitted but noticed that the new one hasn't been attached to the wall, as was the case with the old one. The bracket is there, but it's just not attached to the wall. As a result it's being supported by two pipes above vessel, and boiler case below which causes case to bend a little. If the boiler case is removed, then vessel is effectively just hanging from the pipes, and they move slightly as they adjust to take it's weight. All of this just don't seem right to me. Also I just noticed that the expansion vessel is installed at a slight angle (leaning to the right).
Due to various other issues as well (overheating, leaking pump valves etc), I had Smith and Byford engineer back round next day. He advised that due to the smaller size of this new vessel it wasn't possible to mount bracket to wall, but as it's very light weight it's perfectly fine the way it is and that he 'does it all the time'.
He said he did try to drill holes for mount, but the wall just started crumbling away. I didn't hear no drilling, can't see any new holes and wall is fine (outside brick wall). I pushed the issue further, but he was adamant that it's fine just the way it is, and to fit mount would require lots of pipe work etc. We left it at that, but it's still bugging me, so hopefully you guys can shed your views on this please?
1. Can the two pipes you see in the pictures below adequately support this 8L vessel, or should it be mounted via bracket?
2. If it's ok for pipes to support vessel, is it ok that they move slightly (1-2cm I guess) as they adjust to take full weight of vessel when boiler case is removed?
3. Is it ok that the vessel has been installed at a slight angle, or should it be perfectly straight?
The engineer certainly seemed to know his stuff regarding everything else he explained, but this one thing continues to bug me. As with all council contractors, they always seem to be in a rush due to far too many jobs booked for one engineer to possibly complete in a day. I can therefore understand why things may be missed or shortcuts taken in order to keep bosses happy.
I'm far from knowledgeable regarding this, but it appears for vessel to be mounted, it would have to be removed and perhaps pipes altered, all of which may be an unnecessary job for contractor to complete IF indeed it is perfectly acceptable and safe the way it is. Either way it would be great to get some clarification on this for peace of mind. If current install is not acceptable, what can I can say to convince him that it needs re-installing?
Thanks all
I've had a new 8L expansion vessel fitted but noticed that the new one hasn't been attached to the wall, as was the case with the old one. The bracket is there, but it's just not attached to the wall. As a result it's being supported by two pipes above vessel, and boiler case below which causes case to bend a little. If the boiler case is removed, then vessel is effectively just hanging from the pipes, and they move slightly as they adjust to take it's weight. All of this just don't seem right to me. Also I just noticed that the expansion vessel is installed at a slight angle (leaning to the right).
Due to various other issues as well (overheating, leaking pump valves etc), I had Smith and Byford engineer back round next day. He advised that due to the smaller size of this new vessel it wasn't possible to mount bracket to wall, but as it's very light weight it's perfectly fine the way it is and that he 'does it all the time'.
He said he did try to drill holes for mount, but the wall just started crumbling away. I didn't hear no drilling, can't see any new holes and wall is fine (outside brick wall). I pushed the issue further, but he was adamant that it's fine just the way it is, and to fit mount would require lots of pipe work etc. We left it at that, but it's still bugging me, so hopefully you guys can shed your views on this please?
1. Can the two pipes you see in the pictures below adequately support this 8L vessel, or should it be mounted via bracket?
2. If it's ok for pipes to support vessel, is it ok that they move slightly (1-2cm I guess) as they adjust to take full weight of vessel when boiler case is removed?
3. Is it ok that the vessel has been installed at a slight angle, or should it be perfectly straight?
The engineer certainly seemed to know his stuff regarding everything else he explained, but this one thing continues to bug me. As with all council contractors, they always seem to be in a rush due to far too many jobs booked for one engineer to possibly complete in a day. I can therefore understand why things may be missed or shortcuts taken in order to keep bosses happy.
I'm far from knowledgeable regarding this, but it appears for vessel to be mounted, it would have to be removed and perhaps pipes altered, all of which may be an unnecessary job for contractor to complete IF indeed it is perfectly acceptable and safe the way it is. Either way it would be great to get some clarification on this for peace of mind. If current install is not acceptable, what can I can say to convince him that it needs re-installing?
Thanks all