We've got the shell of an extension at the back of our house, completed by a builder. Roof, walls, concrete floor, etc. -- just no windows or doors.
Throughout the build communication was absolutely rubbish with me constantly having to chase things up, and taking time off work for no-shows. I've never raised it as we are human and he's down to Earth in person. Plus, what's the point in creating friction? Unfortunately there have been other issues such as us having a concrete floor when I specified suspended and using my tools without asking (wheelbarrow, drill) and breaking both! Again, I've begrudgingly let these slip.
I've dealt with the BCO who is a really decent bloke. The current detail he is waiting on is a photo of the floor showing insulation and membrane before the poor. I know this went down and I put them in touch with each other so that the builder could share pictures which he's said twice now that he'll do. The BCO arranged to meet up with the builder to see this, but the builder never showed up.
We are currently awaiting windows. I sent him measurements over 10 weeks ago and he still doesn't have a date. A local firm I trust can get them to me in 2 weeks. I've decided to scrap the builder and do this myself. There's no contract, he has far larger jobs on (we are his smallest!) and I'm a bit fed up of him, especially with a baby on the way.
I still don't have the pictures of the floor pre-pour. Should things go sour and he not provide them, how do I satisfy the BCO short of pulling the floor up? I've asked for them a couple of times this week and still not got them, but not mentioned me wanting to sort the windows myself.
Throughout the build communication was absolutely rubbish with me constantly having to chase things up, and taking time off work for no-shows. I've never raised it as we are human and he's down to Earth in person. Plus, what's the point in creating friction? Unfortunately there have been other issues such as us having a concrete floor when I specified suspended and using my tools without asking (wheelbarrow, drill) and breaking both! Again, I've begrudgingly let these slip.
I've dealt with the BCO who is a really decent bloke. The current detail he is waiting on is a photo of the floor showing insulation and membrane before the poor. I know this went down and I put them in touch with each other so that the builder could share pictures which he's said twice now that he'll do. The BCO arranged to meet up with the builder to see this, but the builder never showed up.
We are currently awaiting windows. I sent him measurements over 10 weeks ago and he still doesn't have a date. A local firm I trust can get them to me in 2 weeks. I've decided to scrap the builder and do this myself. There's no contract, he has far larger jobs on (we are his smallest!) and I'm a bit fed up of him, especially with a baby on the way.
I still don't have the pictures of the floor pre-pour. Should things go sour and he not provide them, how do I satisfy the BCO short of pulling the floor up? I've asked for them a couple of times this week and still not got them, but not mentioned me wanting to sort the windows myself.