Hi
I have been using a building company to clear the site where my extension is going and they have been good at what they have been doing, although I think they may be taking advantage a bit now so a little advice here would be great.
They came and dug a trial hole to about 1.5m last week and said the ground was poor, which was kind of expected as a house down the road had pilings for their extension just two months ago.
The builders indicated that the building inspector (which i have yet to get out) would come out and insist on pilings, although they are saying it won't work as the ground is too tough to pile (brick/stone/rubble/general dumping ground) and it'll be a waste of money to try. They said i'll be best with a raft foundation and they would be at my house when the building inspector arrives to suggest/discuss with him the prospect of a raft.
The extension is a 27m2 footprint (l-shape). I am going to ring for more quotes this week, but they quoted £11,000 for the groundworks to DPC (normal trench foundations to 900mm), £17,000 if it needs pilings to 4m deep (plus extra if they go deeper), and now they are saying it's £2-3k additional to the piles for a raft.
Here are my questions and concerns.
I thought piles could go through pretty much any ground; Is there a chance the piles won't go down and install as required?
The extension isn't massive so £20k for a 27m2 raft, is that a lot?
Anyone had a raft designed and know a rough cost for design from a SE?
Anyone had a raft installed? What did you pay and for what square metre?
Sorry for long post.
I have been using a building company to clear the site where my extension is going and they have been good at what they have been doing, although I think they may be taking advantage a bit now so a little advice here would be great.
They came and dug a trial hole to about 1.5m last week and said the ground was poor, which was kind of expected as a house down the road had pilings for their extension just two months ago.
The builders indicated that the building inspector (which i have yet to get out) would come out and insist on pilings, although they are saying it won't work as the ground is too tough to pile (brick/stone/rubble/general dumping ground) and it'll be a waste of money to try. They said i'll be best with a raft foundation and they would be at my house when the building inspector arrives to suggest/discuss with him the prospect of a raft.
The extension is a 27m2 footprint (l-shape). I am going to ring for more quotes this week, but they quoted £11,000 for the groundworks to DPC (normal trench foundations to 900mm), £17,000 if it needs pilings to 4m deep (plus extra if they go deeper), and now they are saying it's £2-3k additional to the piles for a raft.
Here are my questions and concerns.
I thought piles could go through pretty much any ground; Is there a chance the piles won't go down and install as required?
The extension isn't massive so £20k for a 27m2 raft, is that a lot?
Anyone had a raft designed and know a rough cost for design from a SE?
Anyone had a raft installed? What did you pay and for what square metre?
Sorry for long post.