[GALLERY=media, 16854][/GALLERY] strip foundations 600x200mm

[GALLERY=media, 16855][/GALLERY] stop cock had to be moved
from founds.

[GALLERY=media, 16856][/GALLERY] front elevation existing

[GALLERY=media, 16857][/GALLERY]mesh for founds (clay soil)

[GALLERY=media, 16858][/GALLERY] steel post and found walls.

[GALLERY=media, 16859][/GALLERY] 150mm hardcore.

[GALLERY=media, 16860][/GALLERY] nearly ready for dpm.

[GALLERY=media, 16861][/GALLERY] floor ready

[GALLERY=media, 16862][/GALLERY] 100mm concrete.

[GALLERY=media, 16865][/GALLERY] steel up and kit started.

[GALLERY=media, 16866][/GALLERY] roof trusses up.

[GALLERY=media, 16867][/GALLERY] roof tiled.

[GALLERY=media, 16868][/GALLERY] brickwork started.

[GALLERY=media, 16870][/GALLERY] brickwork.

[GALLERY=media, 16871][/GALLERY] getting there.

[GALLERY=media, 16872][/GALLERY] 1 more day on brickwork.

[GALLERY=media, 16873][/GALLERY] brickwork complete.

[GALLERY=media, 16874][/GALLERY] windows in.

[GALLERY=media, 16875][/GALLERY] inside now.

[GALLERY=media, 16876][/GALLERY] floor insulated.

[GALLERY=media, 16877][/GALLERY] floor down walls insulated.

[GALLERY=media, 16878][/GALLERY] plastering.

[GALLERY=media, 16879][/GALLERY] job complete and telly moved in lol.
 
he wanted to do the skirtings himself...... :D and he's a spark he done the leccy work.
 