Hi
I am hoping you can help me with some independent advice regarding footings that have been dug for a single-story extension at my sons property.
Due to a neighbouring tree roots, we have been advised by the council to dig extra deep footings for the foundations, I'm afraid I don’t have the specific measurements but we are having to go a meter deeper that the original house foundations ☹.
Since the first trenches have been dug, ready for concrete on Wednesday, we have had a lot of rain which has caused some of the walls to partially collapse! Now this is where we are really worrying, one of the partially collapsed walls is against the neighbour’s patio and the other against a public footpath. From what we can some of the material under both the edge of the patio and the footpath have dropped into our trench.
I have attached a number of pictures so you can see what i am trying to explain, any advise would be most helpful.
1 - Should we pump out today and re-shutter the walls or wait until the day before we concrete?
2 - What can we do about the neighbour’s patio and the footpath? Can we “underfill” once the concrete has been poured?
Many thanks
Andy
I am hoping you can help me with some independent advice regarding footings that have been dug for a single-story extension at my sons property.
Due to a neighbouring tree roots, we have been advised by the council to dig extra deep footings for the foundations, I'm afraid I don’t have the specific measurements but we are having to go a meter deeper that the original house foundations ☹.
Since the first trenches have been dug, ready for concrete on Wednesday, we have had a lot of rain which has caused some of the walls to partially collapse! Now this is where we are really worrying, one of the partially collapsed walls is against the neighbour’s patio and the other against a public footpath. From what we can some of the material under both the edge of the patio and the footpath have dropped into our trench.
I have attached a number of pictures so you can see what i am trying to explain, any advise would be most helpful.
1 - Should we pump out today and re-shutter the walls or wait until the day before we concrete?
2 - What can we do about the neighbour’s patio and the footpath? Can we “underfill” once the concrete has been poured?
Many thanks
Andy