Hi,
New to this forum and I'm in the process in building an orangery.
BCO have stated that I need to lay a Gas membrane. I've seen other comments on this site which are extremely useful.
The attached image shows what I think should I need to do however I just wanted to know any thoughts people may have on any foreseeable issues with this layout of the membrane.
The drawing shows the gas membrane overlapping the inner leaf on top of the dpc and then dropping down to the outer leaf by 150mm to ground level.
A weep vent is added.
Would I need a cavity tray that sits above dpc as well?
Is the other solution to lap the inner and outer leaf at dpc level and then add a cavity tray plus weep vent above dpc level?
The diagram is something similar I saw on this forum but don't have the link.
My next stage in the build is to add the sub base mot Type 1 then a 50mm blinding layer before the membrane goes down.
Any help is much appreciated!
New to this forum and I'm in the process in building an orangery.
BCO have stated that I need to lay a Gas membrane. I've seen other comments on this site which are extremely useful.
The attached image shows what I think should I need to do however I just wanted to know any thoughts people may have on any foreseeable issues with this layout of the membrane.
The drawing shows the gas membrane overlapping the inner leaf on top of the dpc and then dropping down to the outer leaf by 150mm to ground level.
A weep vent is added.
Would I need a cavity tray that sits above dpc as well?
Is the other solution to lap the inner and outer leaf at dpc level and then add a cavity tray plus weep vent above dpc level?
The diagram is something similar I saw on this forum but don't have the link.
My next stage in the build is to add the sub base mot Type 1 then a 50mm blinding layer before the membrane goes down.
Any help is much appreciated!