e fulfil all the criteria not to have a buildover agreement. What we need to avoid however is getting down there with a piling machine on site, and finding we're going to need a buildover agreement. Anyone have any suggestions of how we might best establish the sewer position more precisely. I had a cctv survey done, which was beyond useless; is trial pits the only way to be certain
Have you spoken to your water Company?
Build over agreements are really build near agreements.....you need one if you are building within 3m of a public sewer.
To position it you need a thing that goes down the sewer, then you track it with another thing on the ground.
Have you dug down? Are you definitely on shrinkable clay?
I did a job with an oak tree 4 metres away, the client got the soil tested, it was found to be load bearing mudstone lower down and just a 1 metre footing.
For piling, you need: driven piles, they are filled up with concrete and some rebar is cast in so it pokes out the top.
Then a load of rebar with special bends to a schedule is wired in place
Then the whole lot is cast in a concrete skirt
Then you need beam and block suspended flooring.
And you will need a structural engineer to design the piling and ring beam
Alternative is a raft, which again needs an engineer to design, could be more awkward with tree and drain issues. Rafts float around, piles stand on stilts. Neither will move around with the house unless that has same foundation spec.