The original cracked/leaking clay drainage of the house has been disconnected and partially removed, with an inspection chamber installed as described in this thread (thank you to those who so kindly offered advise) We have temporary drainage set up & need to figure out the next step.
This is the original rough plan :
We now have a 450mm inspection chamber where the Buchan trap was, with its invert at approximately 110mm below ground level.
1. Drop Shaft/Back drop connection to Inspection Chamber to deal with overly steep fall (~1in5)
The fall from the current soil pipe location to the inspection chamber inlet is excessive at around 1 in 5. I have found the suggestion on Paving Expert about a back drop connection to the IC, which would enable us to get the 1 in 40 fall up to this point.
Questions :
2. Rainwater gully into soil stack above rest bend? (combined sewage system)
The house is a Victorian terrace & has very shallow foundations. The corner next to the soil stack has already sunk quite a bit due to saturation/washing away of soil from undetected foul water leaks hidden under concrete, potentially over many years & the ground still feels soft here.
We created a quick fix for the initial leak from a cracked clay pipe collar embedded in concrete by angle grinding off the collar then inserting a McAlpine Drain connector like so :
We suspect there may be further damage to the clay pipe joints underground so need to replace with plastic pipe back to the IC. We would like to minimise disturbance and be cautious about digging close or too deep near the shallow victorian foundations.
We have ascertained that the clay rest bend shown in the photo below goes directly underneath the rainwater gully, running perpendicular - right next to these foundations.
Initially I thought we would need a pipe run a little distance away, perpendicular to the wall with 3 x 45° junctions : one for the gully, one for a soil stack rest bend and another gully for the kitchen wastes - possibly with a rodding eye further along :
However, this is only going to be a semi-permanent installation (see below) and whilst I need it to work well & give time for the soil/wall to dry out, it would be good to minimise number of fittings required - since ultimately they are unlikely to remain here.
I hit upon the idea of connecting the gully to a junction above the rest bend like this :
Questions :
3. Future plans for moving bathroom to front of house, understairs toilet & rear extension.
I hope to run drainage under the ground floor, mainly to enable moving the bathroom to the front of the house. I am envisioning a soil stack in the hallway boxed in (possibly slightly chased into wall to reduce its volume) and probably a stub stack under the stairs for toilet & basin (possibly washing machine too if I can fit it in) - the kitchen sink waste could drain into a stub stack here too, since I hope to maybe build a side-return extension at some point.
Might this drainage run arrangement work - with a 250mm sealed access chamber in the kitchen? Any thoughts or suggestions?
I am obviously keen to reduce likelyhood of it blocking - I recognise it is a long run... & also want to ensure there is good rodding access if it does. It potentially will be buried under a limecrete slab in due course (we would probably lay it in the subfloor under the suspended timber floor for now, to get the new bathroom up and running - although we would have to cut a channel through the solid concrete kitchen floor)
Because the bit we are connecting up now will not be there permanently, I am wondering whether we should connect it up to a side inlet of the 450mm inspection chamber - but I know that is poor practice (since you are supposed to have the main channel in use). However, doing so would allow us to put in a drop shaft connection at the same time for the eventual main run through to the soil stack in the hallway, meaning we wouldn't have to dig down so deep (1.2m) again around the IC - we would only have to expose the drop shaft 60cm down or so.
I also realise that the drop shaft in itself could almost act as a small change of direction - in other words the rest bend connecting to the inlet would stay static, but the top pipe and rodding access could 'rotate' slightly. Any thoughts on this? I'm guessing this is poor practice again and could cause problems. Doing so would enable us to 'switch' the run above the drop shaft over from the side return to the hallway soil stack when everything is in place.
Anyway - sorry for massive post. Any thoughts appreciated.
This is the original rough plan :
We now have a 450mm inspection chamber where the Buchan trap was, with its invert at approximately 110mm below ground level.
1. Drop Shaft/Back drop connection to Inspection Chamber to deal with overly steep fall (~1in5)
The fall from the current soil pipe location to the inspection chamber inlet is excessive at around 1 in 5. I have found the suggestion on Paving Expert about a back drop connection to the IC, which would enable us to get the 1 in 40 fall up to this point.
Questions :
- Is this the best option?
- Are they prone to blockage? I also worry that waste might regularly overshoot the junction/drop?
- Is a rest bend the preferred option? One image on paving expert shows a 90° knuckle bend, the other connecting to a plastic IC shows a rest bend. Another option is a 'ramped connection' as shown in the second image, although this will make it even closer to the house, which might be a problem.
2. Rainwater gully into soil stack above rest bend? (combined sewage system)
The house is a Victorian terrace & has very shallow foundations. The corner next to the soil stack has already sunk quite a bit due to saturation/washing away of soil from undetected foul water leaks hidden under concrete, potentially over many years & the ground still feels soft here.
We created a quick fix for the initial leak from a cracked clay pipe collar embedded in concrete by angle grinding off the collar then inserting a McAlpine Drain connector like so :
We suspect there may be further damage to the clay pipe joints underground so need to replace with plastic pipe back to the IC. We would like to minimise disturbance and be cautious about digging close or too deep near the shallow victorian foundations.
We have ascertained that the clay rest bend shown in the photo below goes directly underneath the rainwater gully, running perpendicular - right next to these foundations.
Initially I thought we would need a pipe run a little distance away, perpendicular to the wall with 3 x 45° junctions : one for the gully, one for a soil stack rest bend and another gully for the kitchen wastes - possibly with a rodding eye further along :
However, this is only going to be a semi-permanent installation (see below) and whilst I need it to work well & give time for the soil/wall to dry out, it would be good to minimise number of fittings required - since ultimately they are unlikely to remain here.
I hit upon the idea of connecting the gully to a junction above the rest bend like this :
Questions :
- Is this allowed (building regs)?
- Is it a good, bad or terrible idea?
- I have put a single socket access pipe just above ground level - this would allow rodding access and a socket for kitchen 40mm waste to go into. Useful or unnecessary? (could just use solvent weld strap boss)
3. Future plans for moving bathroom to front of house, understairs toilet & rear extension.
I hope to run drainage under the ground floor, mainly to enable moving the bathroom to the front of the house. I am envisioning a soil stack in the hallway boxed in (possibly slightly chased into wall to reduce its volume) and probably a stub stack under the stairs for toilet & basin (possibly washing machine too if I can fit it in) - the kitchen sink waste could drain into a stub stack here too, since I hope to maybe build a side-return extension at some point.
Might this drainage run arrangement work - with a 250mm sealed access chamber in the kitchen? Any thoughts or suggestions?
I am obviously keen to reduce likelyhood of it blocking - I recognise it is a long run... & also want to ensure there is good rodding access if it does. It potentially will be buried under a limecrete slab in due course (we would probably lay it in the subfloor under the suspended timber floor for now, to get the new bathroom up and running - although we would have to cut a channel through the solid concrete kitchen floor)
Because the bit we are connecting up now will not be there permanently, I am wondering whether we should connect it up to a side inlet of the 450mm inspection chamber - but I know that is poor practice (since you are supposed to have the main channel in use). However, doing so would allow us to put in a drop shaft connection at the same time for the eventual main run through to the soil stack in the hallway, meaning we wouldn't have to dig down so deep (1.2m) again around the IC - we would only have to expose the drop shaft 60cm down or so.
I also realise that the drop shaft in itself could almost act as a small change of direction - in other words the rest bend connecting to the inlet would stay static, but the top pipe and rodding access could 'rotate' slightly. Any thoughts on this? I'm guessing this is poor practice again and could cause problems. Doing so would enable us to 'switch' the run above the drop shaft over from the side return to the hallway soil stack when everything is in place.
Anyway - sorry for massive post. Any thoughts appreciated.
Last edited: