Hi,

All the answers to questions I see which ask about when you can walk on screed after laying, typically say 24-48 hours (or as little as 12 for a special type).

But this is described as being for ‘light traffic’.

I just want to walk over mine ONCE. The floor is 4.6m across.

So, never mind ‘light traffic’… when can I cross one time (and back)?



Thanks!
 
You've not mentioned what kind of screed you have, or how heavy you are.

If it was poured/laid today, you could walk over it in the morning, prod it with a stick to see if it's dried any sooner.

(y):LOL:
 
You've not mentioned what kind of screed you have, or how heavy you are.

If it was poured/laid today, you could walk over it in the morning, prod it with a stick to see if it's dried any sooner.

(y):LOL:
Unfortunately I don’t know what type of screed it is. But I’m 11.5 stone
 