Hi all,
I am carrying out a major re-decor of my home. Below is the order that I shall be carrying out the works in my home. I would appreciate if anyone could give me their opinion on my order; Whether this is the best way or not or just give recommendations, I would be very grateful for your information and reasons why.
I thought this order below would be the best way; to prevent any inconvenience to other jobs having to be re-done again.
1. Full Central Heating system
2. Garden Paving
3. Guttering Around the House
4. Ceiling Velux window in the extension downstairs
5. Doors + Architraves
6. Plastering some Ceilings due to cracks
7. Wall conditions prep walls (Plaster or fill) depending on severity, prep for paint
8. New light replacements and socket and switch replacements.
9. Painting
10 Fix Floor boards and install laminate flooring/ skirting and carpet.
I am having the (Upstairs) bathroom changed putting in a new suite; where would this and a new kitchen installation (Downstairs) Prioritise in my list above ?. Please see below in more detail regarding my kitchen.
I am also having a new kitchen installed. The current floor tiles and kitchen shall be removed. The kitchen room shall be like a blank canvas, therefore, should the new floor tiles be installed first, then the new kitchen cupboards etc.. to be installed on top of the tiles ? or should the kitchen be installed on the concrete then floor tile around after (vice versa)?
Because the old Kitchen floor tiles will be removed where should I prioritize this in my list above? I would assume the job would be messy removing and re-tiling etc...I would appreciate all your advice and opinion on this and my order of work.
Thank you so much, advance.
I am carrying out a major re-decor of my home. Below is the order that I shall be carrying out the works in my home. I would appreciate if anyone could give me their opinion on my order; Whether this is the best way or not or just give recommendations, I would be very grateful for your information and reasons why.
I thought this order below would be the best way; to prevent any inconvenience to other jobs having to be re-done again.
1. Full Central Heating system
2. Garden Paving
3. Guttering Around the House
4. Ceiling Velux window in the extension downstairs
5. Doors + Architraves
6. Plastering some Ceilings due to cracks
7. Wall conditions prep walls (Plaster or fill) depending on severity, prep for paint
8. New light replacements and socket and switch replacements.
9. Painting
10 Fix Floor boards and install laminate flooring/ skirting and carpet.
I am having the (Upstairs) bathroom changed putting in a new suite; where would this and a new kitchen installation (Downstairs) Prioritise in my list above ?. Please see below in more detail regarding my kitchen.
I am also having a new kitchen installed. The current floor tiles and kitchen shall be removed. The kitchen room shall be like a blank canvas, therefore, should the new floor tiles be installed first, then the new kitchen cupboards etc.. to be installed on top of the tiles ? or should the kitchen be installed on the concrete then floor tile around after (vice versa)?
Because the old Kitchen floor tiles will be removed where should I prioritize this in my list above? I would assume the job would be messy removing and re-tiling etc...I would appreciate all your advice and opinion on this and my order of work.
Thank you so much, advance.