Before I lay my 100mm MOT compacted hardcore for patio base what do I need to do with these? (If anything)
1. Red string line is top of hardcore once compacted
There is a big concrete slab of some sort (connected to old drain which is to the top right of it - 1 o’clock position)
The hardcore will obviously be sitting on top of this slab - is that okay or so I need to smash the concrete/brick up so the hardcore can compact into something?
3. I’ve dug a small channel for my armoured cable (supplying log cabin) to sit in before laying hardcore.
Can I lay compacted hardcore directly onto this cable or do I need to cover with a bit of soil first?
Cheers
1. Red string line is top of hardcore once compacted
There is a big concrete slab of some sort (connected to old drain which is to the top right of it - 1 o’clock position)
The hardcore will obviously be sitting on top of this slab - is that okay or so I need to smash the concrete/brick up so the hardcore can compact into something?
3. I’ve dug a small channel for my armoured cable (supplying log cabin) to sit in before laying hardcore.
Can I lay compacted hardcore directly onto this cable or do I need to cover with a bit of soil first?
Cheers