4m rsj went in Tuesday and the 10mm gap between steel and existing brickwork above was packed with 3:1 sharp sand:cement (very dry, just clumping). Also banged in some slate where I could get a tight fit.
This is indoors so heated each evening. The mortar felt as hard as a rock 24 hours later. It’s now Sat morning so it’s been 80 hours. Am I ok to remove Acrows?
This is indoors so heated each evening. The mortar felt as hard as a rock 24 hours later. It’s now Sat morning so it’s been 80 hours. Am I ok to remove Acrows?