Week 5
Progress has been hampered this week by heavy rain and a flu bug. But more of the wall has gone up, and some internal blockwork..
Note the openings for the French doors and the utility window (who would have thought of having a window there? Eh Kev!?). We are going to reuse the existing utility window.
The warm air central heating unit was removed on Monday. It's a bit of a beast.
The hole in the ground was where the fan sat, connected to an underfloor duct for drawing air into the heater, from the main house.
We are replacing the warm air unit with a combined warm air, hot water, and radiator system. this will be located in the garage. I shall cover the new central heating system in more detail at a later stage, but here is the basic system schematic.
This system should be a lot more efficient and controllable than the old warm air only system.