Once the kitchen was squared away, I had a damn good clear up, swept the floor and started working on installing the laminate flooring... Common sense would've suggested starting from the wall with the kitchen & bathroom. However when I worked out the sizing etc it would have resulted in several awkward cuts etc. So I started on the long clear wall, laying front to back from the main patio doors.
I made pretty quick progress of getting the laminate down, despite finding pretty much an entire pack that had chipped corners. I think I've got enough to finish off though
Pretty much half-way. Had to keep juggling the mitre saw and stuff around so that I had space to work, as the weather wasn't great outside.
I ended up cutting out around the kitchen cabinet legs so that I could get a full width board in-place:
Looks pretty smart I think
I did end up with a tiny slither on the door opening
I looked at a few different options for finishing this off, and in the end decided to have the joint in the middle of the width of the door opening, as it should be largely hidden there:
Not the most obvious, but there was a lot to cut out on this board:
It was at this point that I'd discovered another f*ck up that I'd made. I forgot to install the drainage for the kitchen waste.
So I pulled the sink unit out, cut the DPM out to reveal the 117mm hole that I cut when installing the floor, and discovered another issue! I'd put the stop-cock smack bang in the middle of the drain.
Cue a swift relocate of the stop-cock, and the drainage dropped into place nicely...
And it even cleared the cut-out in the kitchen cabinet:
Next, I cut the worktop to size, and test fitted it in place:
Once I was happy with the fit, I marked out for the sink and started to cut it out with a jig-saw.
Note the temporary bracing there to prevent the cut piece from simply dropping through...
And wallah, we have a kitchen sink:
Starting to come together:
I've also fitted the end-panel and deco moulding on the microwave cupboard. Later there will be an LED strip mounted under this cupboard for some lighting.
I also ordered the microwave, and got that installed quickly:
And started working on the plumbing under the sink... This is going to get pretty tight, as I've got a 10l water heater unit plus expansion vessel to fit under here, plus the drainage for the sink and PRV on the water heater..
Started working out where the drainage and PRV needs to be:
I've also drilled and mounted the tap, but don't seem to have a picture...
Next job is to finish off the plumbing under the sink, and then move onto fitting the toilet in the bathroom...
I'm hoping to be moved in before Christmas, so still got a little way to go...
I did have a new toy, I mean essential tool, delivered today - a Ryobi 18g brad nailer so that I can make light work of installing the skirting and architrave.
Oh, and the Cedral Lap cladding that I ordered for 3 of the 4 walls, all 50 boards plus profiles etc, turned up on Friday, so that hopefully I can try and start fitting that if I get some reasonable weather...