Ok, time for the next instalment - steels!!!
My Structural Engineer did an amazing job in supporting me as a dumb DIYer through this whole process and reworking things and solving problems when they occurred.
My overall RSJ design was as follows:
In addition to pages of calculations, I also got loads of helpful diagrams of actually how to fix/implement the above plan. With the view of saving the picture count, I've combined a couple of examples onto a single screenshot along with the listing of steels that I ordered from the local steel supplier (Alexander Steel Liverpool if anyone is local)
2 weeks and £1,700 later all these arrived on my drive. I was concerned with the big steels how they'd get them off the truck, I was thinking I'd need a crane or something but two guys turned up with them all loaded onto the back of a flatbed truck, and with a bit of assistance from me and the other half, these were all whipped off the back of the truck in about 20 minutes flat. Lots of shimmying and pivoting from one end rather than lifting/carrying of the whole weight of the RSJs.
After getting inspiration from
@JPBlackie in this thread
https://www.diynot.com/diy/threads/moving-an-rsj-660kg.549936/ we also used the cut up round fencepost method to shift the steels around the sight into the right positions for lifting. The two steels with the welded plates on them were by far the heaviest ones to move around/list, but rolling them round on the fence posts really did make it a doddle to get close to where they needed to go.
I'd been collecting cheap acro props on eBay, paying between £7 & £10 quid for them and avoiding the really rusty ones, as I didn't know how long I'd need the for it's better than hiring them at £20 per week. After buying a couple of full price XL stongboys new, I then found a chap selling 9 in Manchester for £175 ... so I've ended up with 11 XL strongboys which was way more than the 5 I needed, but one day they'll go back on eBay
. I went for the XL stongboys because they can support two skins from one side, but I just wanted a bit more room between the existing wall/pilars and the acro props when I was lifting the beam into position.
In the picture below I'd stitch drilled the bricks out using my SDS (and not cleaned up at the point of taking the photo). The acros you see in the photo below were just there temporarily to support the brickwork above the piers.
One thing that seems obvious now, but hadn't occurred to me beforehand (despite seeing all the measurements) was that all these RSJs were too long to fit into the rooms in which they were suppose to go as obviously they are the width of the room plus the bearings. Hence why you see the RSJ diagonally in the room.
Another thing I'd not thought of, but the guy who sold me the acros helpfully mentioned, was that because my wish to leave the existing walling in place that I'd need a cantilevered genie lift to raise the beams up, as these have additional weights that extend behind them but mean that there are no legs that project forward of the lifting arms - meaning you can get close up to the wall you're lifting onto.
Oh, and another thing I'd not realised was how difficult it would be to move the RSJs once they were lifted on the lift. The genie lift itself was a beast and really heavy, but with the beam loaded it was virtually impossible to move more than a couple of inches backwards and forwards, and literally no chance of manoeuvring it sideways to where you actually wanted it to be!
Probably not the ways the pros would do it, but I improvised by lifting the RSJs up as high as they would go on the genie lift, then rolling my scaffold tower underneath the beam before lowering it onto the scaffold tower at a height that meant the RSJ cleared the two walls.
Although the scaffold tower wheels didn't like it too much, I was then able to wheel the RSJ pretty much into the right position for the wall before bringing the genie lift back in at a 90 degree angle to the wall ready for the final list into position.
You can just about see in the picture above that I'd had the evolution disc cutter out at this point to cut the mortar/brickwork where the acros were going to go.
I'd rested the the RSJ temporarily on the two walls of the extension close enough to the wall it would be support in order to get the acros in behind it, but with enough space for me to finish off the cuts into the house wall to remove the brickwork where the RSJs would go. The big 203 x 203 you see below with the plate on top would not only be supporting both skins of the existing house wall you see, but inbetween the 3rd and 4th acro props where the bigger cut out is, there would be the two RSJs to support the new first floor walls as well.
Although I didn't take a picture, there are also 4 acros / strongboys inside the original kitchen with some 4 x 2 timber supporting the floor joists.
Now the next bit was an absolute nightmare to be honest! The final movement of no more than 30cm backwards from the photo above to get the RSJ into position must have taken about 2 hours of grunting, shouting and swearing. The genie lift would not move straight back the way I wanted it to. It was like that dodgy trolley you get at the supermarket where the wheels send you off in different directions each time you push.
I'm sure there's probably a knack to it, but getting the steel in so that the steel plate was supporting both skins correctly, there was sufficient baring on each pillar and that the thing was actually level took a long time and so many attempts I lost count.
However, we finally got there and I banged a couple more acro props/strongboys in place underneath the RSJ to hold it in place. I then fitted the pad stones and mortar'ed the pad stones and a number of bricks above the beam back into place.
I didn't get to many photos at this stage, but the one below as the next RSJs started to go in shows the main 203 x 203 in place.
As per the picture below, again we had to get creative for the 4 x 254 x 146 RSJs that would be holding up the first floor walls of the extension to get them into position, because of the same issue of them being longer than the rooms they were going into and the inability to move the genie lift around once loaded.
As there is a wall between the garage and the kitchen, the two rear RSJs took the most steps to get into place. The process was:
1. RSJ Rolled into garage on fence posts
2. Lifted on genie lift and then lowered onto scaffold tower that was moved under the genie lift.
3. Scaffold tower wheeled to be flush with the kitchen/garage wall
4. Genie lift relifted the RSJ, and scaffold tower removed.
5. Genie lift pushed/manhandled forward so that RSJ was over the other side of the kitchen garage wall (this bit was proper sketchy as the RSJ had to be on the very end of the lifting arms to be able to get enough clearance to get it over the wall!)
6. Scaffold tower erected on kitchen side of wall and RSJ lowered back onto scaffold tower.
7. Genie lift moved from garage to kitchen and then relift the RSJ.
8. Via trial and error work out how much 'stuff' needed to go onto the scaffold tower to get the RSJ at the correct height to go into it's final position, before lowering the RSJ back onto stuff (see the blocks and metal work in the picture below)
9. Roll scaffold tower into final position with RSJ's having the right baring.
10. Use genie lift again to get just enough heigh to remove some 'stuff' so that the RSJ reseted in correct position
The repeat all the palaver above for the second RSJ, but now with the first RSJ in the way as well just to make it more awkward!
Same RSJ with the stuff to get it into position below.
Here it is with both RSJs in place for the rear wall for the first floor. There's a small RSJ with a padstone on top on this side as the 1st floor wall is at right angles to where the back door for the new kitchen will be.
I made a screw-up at this point that I popped the bolts in for the timber that would be my ledger board, but I didn't have the wood at the time. I should have fitted the wood into the web of the RSJ at this point to make my life easier...but I just didn't think about it at the time, so this lead to some faffing around later to retro-fit 8x3 timber and get it bolted in properly.
At this point I'd done one final lift with the genie lift for the day to lift these two RSJs together in order to reused my scaffold tower and 'stuff' to get the RSJs level and mortar'd in, leaving it overnight to set.